Following the February 2012 Earthquake, the dwelling and garage had been demolished, leaving only the garage slab and the driveway at the top of the steep section.  A retaining wall was required to enable the new house to be built on the section. 

With neighbouring properties and dwellings close by on 3 sides of the property, the only access was via the existing driveway at the top of the site, accessed off the Brae. As the retaining wall was adjacent to the existing garage slab, this also had to be stabilised before the work on the wall could begin.

HGM were engaged to construct a 5m high anchored retaining wall . This project included:

  • Installing self-drilling micro piles to secure the garage slab already in place and grouting the cavity inside the slab
  • Drilling, installing and grouting 34 anchors , approx252.5 linear metres drilled
  • Drilling 24 holes for the timber poles, a total of 47.5m and installation and Installation and concreting of 375mm poles
  • Installation of rails on retaining wall, drainage and backfill and temporary hand rail.

Location

24 The Brae, Mt Pleasant, Christchurch

Client

March to October 2017 ( approx. 7 months)

Date

2017

Strong reputation for practical and reliable solutions

From steep hill stabilisation to remote backcountry builds, from power infrastructure to recreation spaces — we specialise in complex, high-risk, technically demanding projects across Canterbury and the wider South Island.

Our services

Power Infrastructure

Power Infrastructure

Recreation Construction

Recreation Construction

Bridge Construction & Maintenance

Bridge Construction & Maintenance

Piling

Piling

Design, Build, and Project Management

Design, Build, and Project Management

Slope Retention

Slope Retention

Marine Services

Marine Services

Timber & Concrete Structures

Tower & Pole Erections

Well Capping

Well Capping

Excavation & Siteworks

Excavation & Siteworks